| Particulars | Details |
|---|---|
| Title |
Mtps I Mill Plant Unit Iv Cutting Removing Of Existing Worn Out Mill Separator Curved Liners And Erection Of New Ms Liners In Mill 4 A To 4 F During Aoh 2024 25
|
| Description |
Mtps I Mill Plant Unit Iv Cutting Removing Of Existing Worn Out Mill Separator Curved Liners And Erection Of New Ms Liners In Mill 4 A To 4 F During Aoh 2024 25
|
| Organisation | TNEB Limited | State Govt. and UT |
| Tender Id | 2024_EB_462462_1 |
|
Reference Number |
CE / MTPS-I / SE / M-I / MP /OT.90/ 2024-25 |
| Tender Fee | 0 |
| EMD | 3900 |
| Tender Value | - |
| Place | Mettur Thermal Power Station-I / Mettur Dam |
| Link |
View Original Tender Notice
https://tntenders.gov.in/nicgep/app?page=FrontEndTenderDetailsExternal&service=page&tnid=549629 |
| Start Date | July 12, 2024 22:30 |
| End Date |
Expired
18/07/2024
Expired 818 days ago |
Tender Support
Get help with filing, GeM registration, documents, or relevant tender alerts.
Mtps i mill plant unit ii overhauling of gravimetric feeders and clean out conveyor of mill 2a to 2f during aoh 2026 2027
Mtps i mill plant unit ii overhauling of gravimetric feeders and clean out conveyor of mill 2a to 2f during aoh 2026 2027
Read moreMtps i mill plant ii complete overhauling of gearbox mechanical face seal assembly worm shaft assembly replacing the worn out bulged insulation cover plate assembly scrapper assembly and worn out flexi coupling etc in mills 2a to 2f during aoh
Mtps i mill plant ii complete overhauling of gearbox mechanical face seal assembly worm shaft assembly replacing the worn out bulged insulation cover plate assembly scrapper assembly and worn out flexi coupling etc in mills 2a to 2f during aoh
Read moreMtps i mill plant unit ii complete dismantling and assembling of mill internals reconditioning renewal of worn out parts bearings replacement of worn out worm wheel with worm shaft and renewal of worm gear hub etc in any one mill 2a to 2f
Mtps i mill plant unit ii complete dismantling and assembling of mill internals reconditioning renewal of worn out parts bearings replacement of worn out worm wheel with worm shaft and renewal of worm gear hub etc in any one mill 2a to 2f
Read moreMtps i bm unit ii boiler aoh 2026 reconditioning and hard facing of used and worn out coal nozzles fixing of divider plates and allied works
Mtps i bm unit ii boiler aoh 2026 reconditioning and hard facing of used and worn out coal nozzles fixing of divider plates and allied works
Read moreMtps i mill plant unit ii dismantling of existing elliptical feeder discharge chutes in mill 2c 2d reconditioning of released ss elliptical feeder discharge chutes and reassembling the same during aoh 2026 27
Mtps i mill plant unit ii dismantling of existing elliptical feeder discharge chutes in mill 2c 2d reconditioning of released ss elliptical feeder discharge chutes and reassembling the same during aoh 2026 27
Read moreMtps i mill plant unit ii strengthening rectification of raw coal bunkers 2a 2b 2c leak arresting work by patch welding and providing stiffeners during aoh 2026 27
Mtps i mill plant unit ii strengthening rectification of raw coal bunkers 2a 2b 2c leak arresting work by patch welding and providing stiffeners during aoh 2026 27
Read moreMtps i mill plant unit ii overhauling of classifier assemblies replacement repairing of eroded inner cone inner cone drum section venture vanes venturi collars during aoh 2026 27
Mtps i mill plant unit ii overhauling of classifier assemblies replacement repairing of eroded inner cone inner cone drum section venture vanes venturi collars during aoh 2026 27
Read moreMtps i mill plant unit ii overhauling of tramp iron chute knife edge gate valves strengthening of reject chute mouth area at under bowl and repairing the cracks of tramp iron chute outside the mill base of mills renewal of the worn out mill
Mtps i mill plant unit ii overhauling of tramp iron chute knife edge gate valves strengthening of reject chute mouth area at under bowl and repairing the cracks of tramp iron chute outside the mill base of mills renewal of the worn out mill
Read moreMtps i bm unit ii boiler pressure parts aoh 2026 reconditioning and hard facing of used and worn out square coal nozzle tips including ss309 plates and checking of deformation and matching with nozzle
Mtps i bm unit ii boiler pressure parts aoh 2026 reconditioning and hard facing of used and worn out square coal nozzle tips including ss309 plates and checking of deformation and matching with nozzle
Read moreMtps i mill plant unit ii dismantling and assembling of coal pipes with bends and renewal of eroded pipes of length at about 15 mtr length along with bends between mill outlet elbow and fuel inlet elbow during aoh 2026 27
Mtps i mill plant unit ii dismantling and assembling of coal pipes with bends and renewal of eroded pipes of length at about 15 mtr length along with bends between mill outlet elbow and fuel inlet elbow during aoh 2026 27
Read moreof your Industry type