Tender Details
Particulars | Details |
---|---|
Title |
Erection 440 V O/H Line From Chp Sbc(ii)rep.Maint. And Replcement 440 V/220 V Lighting O/H Line Npc(iii) O/H Line From Tocp Coal Dump To Pahari Patch For Lighting Pupose Tmc(i V)rep. Changing Of Damaged Pole And Conductor 550 V/440 V Knc
|
Description |
Towards Erection Of New 440 V O/H Line From Chp Substation Lighting Line For Ocp At Sendra Bansjora(ii)maint. Rep. And Replacement Of 440 V/220 V Lighting O/H Line Different Location Npc(iii)erection Of Power O/H Line From Tocp Coal Dump To Pahari Patch
|
Organisation | Bharat Coking Coal Limited | Public Sector Undertakings |
Tender Id | 2025_BCCL_327360_1 |
Reference Number |
GM/SA/AM(EnM)-NIT/2024-25/178 |
Tender Fee | 0 |
EMD | 12283 |
Tender Value | |
Place | SBC,NPC,TMC and KNC under Sijua |
Link | https://coalindiatenders.nic.in/nicgep/app?page=FrontEndTenderDetailsExternal&service=page&tnid=339294 |
Start Date | January 31, 2025 22:30 |
End Date |
11/02/2025 ( Expired 91 days ago ) Search Similar tenders? |
Join for More Relevant Opportunities |
(a) erection of 220v lt o/h line lighting for haul road 9 seem and old deco patch of abocp mine (b) erection of earth wire/cradle guard for safety purpose 6.6 kv d/l feeder near jocp sub-station of abocp mine
(a) erection of 220v lt o/h line lighting for haul road 9 seem and old deco patch of abocp mine (b) erection of earth wire/cradle guard for safety purpose 6.6 kv d/l feeder near jocp sub-station of abocp mine
Read moreWork for erection of new 3.3kv o/h line from tocp substation to pahari patch tetulmari colliery
For erection of new 3.3kv o/h line from tocp substation to pahari patch tetulmari colliery under sijua area
Read more(a)dismantling and erection of lt 220v o/h line in ob dump,coal dump,ripper face and haul road (b)dismantling and erection of lt 220v o/h line in 4thpatch,obdump,coal dump and dumper yard for lighting purpose at socp patch, muraidih,amp colliery.
(a)dismantling and erection of lt 220v o/h line in ob dump,coal dump,ripper face and haul road (b)dismantling and erection of lt 220v o/h line in 4thpatch,obdump,coal dump and dumper yard for lighting purpose at socp patch, muraidih,amp colliery.
Read more(a)dismantling of 6 nos. pole and 8 mtrs. 220 x 2 wire o/h line and re-erection of 9 no. pole and 8 mtrs 220 x 2 wire o/h conductor(b) erection of 09 pole 450 mtrs x 2 wire o/h conductor of 220 v from new 6 no.incline sub-station at 6 no. attendance
(a)dismantling of 6 nos. pole and 8 mtrs. 220 x 2 wire o/h line and re-erection of 9 no. pole and 8 mtrs 220 x 2 wire o/h conductor(b) erection of 09 pole 450 mtrs x 2 wire o/h conductor of 220 v from new 6 no.incline sub-station at 6 no. attendance
Read moreDismantling /erection of pole with changing of damage stay, pin insulator and conductor of 440 v o/h line from garhi filter pump house to intake well under chp-cpp/ppr.
Dismantling /erection of pole with changing of damage stay, pin insulator and conductor of 440 v o/h line from garhi filter pump house to intake well under chp-cpp/ppr.
Read moreRep.and maint. o/h line 220/440v loyabad coke plant(ii)diverison o/h lighting line 6 pit lbc(iii)installation of 440v o/h line 220v siding and office(iv)supply to camera,rfid and lighting led fitting to dump siding(v) erection of 440vbsp(vi)maint o/h
Repairing and maint. of o/h line 220v/440v lighting line different location lbc(ii)di of o/h line 6 pit lbc(iii)installation of 440v o/h line sb siding and 220v o/h sbc office(iv)power supply to camera,rfid and lighting led fitting to dump
Read more(a) repairing of 440v 4 wire mtrs o/h line from golden sub-station to office dhowrah dhowrahand (b) erection of 400 volt o/h line to provide supply to newly installed mobile crusher of 09 nos siding and (c) dismantling of 3 nopipe pole and 320 mtr x
(a) repairing of 440v 4 wire mtrs o/h line from golden sub-station to office dhowrah dhowrahand (b) erection of 400 volt o/h line to provide supply to newly installed mobile crusher of 09 nos siding and (c) dismantling of 3 nopipe pole and 320 mtr x
Read more(a) changing of damaged poles and conductors of 440v o/h line in khodovally and bahaldih basti and (b) dismantling and erection of 220v o/h line for lighting purpose of coal dump.dumper yard, ob dump and chitahi road of socp under muraidih.ampc.
(a) changing of damaged poles and conductors of 440v o/h line in khodovally and bahaldih basti and (b) 
 dismantling and erection of 220v o/h line for lighting 
 purpose of coal dump.dumper yard, ob dump and chitahi road of socp under muraidih.ampc.
Read more(a)erection of 2 nos 1250 amps. a.b.switch of 3.3 kv grade and 4 nos. pipe pole(b) dismantling of 280 mtrs x 4 wire old and damaged overhead conductor of 440 volt(c) dismantling of (i) 10 nos. 440v o/h line from durga mandir sub-station to gokul park
(a)erection of 2 nos 1250 amps. a.b.switch of 3.3 kv grade and 4 nos. pipe pole(b) dismantling of 280 mtrs x 4 wire old and damaged overhead conductor of 440 volt(c) dismantling of (i) 10 nos. 440v o/h line from durga mandir sub-station to gokul park
Read more(a)dismantling and erection of lt 220v o/h line in ob dump,coal dump,ripper face and haul road (b)dismantling and erection of lt 220v o/h line in 4thpatch,obdump,coal dump and dumper yard for lighting purpose at socp patch, muraidih,amp colliery.
(a)dismantling and erection of lt 220v o/h line in ob dump,coal dump,ripper face and haul road (b)dismantling and erection of lt 220v o/h line in 4thpatch,obdump,coal dump and dumper yard for lighting purpose at socp patch, muraidih,amp colliery.