Tender Details

Particulars Details
Title
Construction Of Lilo Of 01 Circuit From 220 Kv D/C Ratangarh (400 Kv Gss) Khetri Line At 220 Kv Gss Jhunjhunu(approx. 1.5 Km) On Labour Contract Basis
Description
Construction Of Lilo Of 01 Circuit From 220 Kv D/C Ratangarh (400 Kv Gss) Khetri Line At 220 Kv Gss Jhunjhunu(approx. 1.5 Km) On Labour Contract Basis
Organisation RRVPN - CMD | State Govt. and UT
Tender Id 2025_RRVPN_445034_1
Reference
Number
1310002404
Tender Fee 3540
EMD 66533
Tender Value
Place Babai
Link https://eproc.rajasthan.gov.in/nicgep/app?page=FrontEndTenderDetailsExternal&service=page&tnid=799264
Start Date February 03, 2025 20:30
End Date

13/02/2025 ( Expired 66 days ago )

Search Similar tenders?
Join for More
Relevant Opportunities
Similar Tenders
Ie services for construction of 6-lane greenfield highway ing from its junction with nh-4b (new nh-348) near pagote (km.0.000) till its junction on nh-48 at chowk (km.29.219) in maharashtra to be d on bot (toll) mode under nh (o)

Ie services for construction of 6-lane greenfield highway ing from its junction with nh-4b (new nh-348) near pagote (km.0.000) till its junction on nh-48 at chowk (km.29.219) in maharashtra to be d on bot (toll) mode under nh (o)

Read more
Design and execution for construction of 400 m length avalanche protection system at km 5.550 to km 5.660, km 7.900 to km 7.950, km 27.200 to km 27.280, km 28.370 to km 28.460 and km 29.200 to km 29.270 on d-s rd i.e. approach road to shinkunla tnl

Design and execution for construction of 400 m length avalanche protection system at km 5.550 to km 5.660, km 7.900 to km 7.950, km 27.200 to km 27.280, km 28.370 to km 28.460 and km 29.200 to km 29.270 on d-s rd i.e. approach road to shinkunla tnl

Read more
Termination of the lilo of 220 kv sherpur jhajra at 120 mw vyasi hep ujvnl for direct at 400 kv substation sherpur pgcil with a line length of apx 2.5 km partially o h approx. 1.5 km with multi-circuit towers and partially with ug apx length 1 km

Termination of the lilo of 220 kv sherpur jhajra at 120 mw vyasi hep ujvnl for direct at 400 kv substation sherpur pgcil with a line length of apx 2.5 km partially o h approx. 1.5 km with multi-circuit towers and partially with ug apx length 1 km

Read more
Construction of 220 kv gss at ia kota (upgradation) (distt. kota) along with associated bays on turnkey basis

Construction of 220/132 kv, 1x200 mva substation at ia kota (upgradation) (distt. kota) along with associated bays on turnkey basis under bn-9018002440

Read more
Construction of four lane road over bridge (rob no. 413) on new b.g. line from khurda road- bolangir and its approaches at km. 134.274 (charichhak) of nh-57 in the state of odisha on epc mode

Construction of four lane road over bridge (rob no. 413) on new b.g. line from khurda road- bolangir and its approaches at km. 134.274 (charichhak) of nh-57 in the state of odisha on epc mode

Read more
Construction of four lane road over bridge (rob no. 399) on new b.g. line from khurda road-bolangir and its approaches at km. 138/435 (village kardakotha) of nh-57 in the state of odisha on epc mode

Construction of four lane road over bridge (rob no. 399) on new b.g. line from khurda road-bolangir and its approaches at km. 138/435 (village kardakotha) of nh-57 in the state of odisha on epc mode

Read more
Construction of four lane road over bridge (rob no. 357) on new b.g. line from khurda road-bolangir and its approaches at km. 156/088 (village baringi) of nh-57 in the state of odisha on epc mode

Construction of four lane road over bridge (rob no. 357) on new b.g. line from khurda road-bolangir and its approaches at km. 156/088 (village baringi) of nh-57 in the state of odisha on epc mode

Read more
Construction of toll plaza at ch. 80.100 near narsi namdeo on risod to hingoli from km 44.220 to km 97.450 section of nh 461 b in the state of maharashtra on risk and cost of contractor on epc basis mode.

Construction of toll plaza at ch. 80.100 near narsi namdeo on risod to hingoli from km 44.220 to km 97.450 section of nh 461 b in the state of maharashtra on risk and cost of contractor on epc basis mode.

Read more
Construction of 01 no. 220kv and 3 nos. 132kv transmission lines for 220 kv gss lamba jatan (upgradation) on turnkey basis under bn-9018002443

Construction of 01 no. 220kv and 3 nos. 132kv transmission lines for 220 kv gss lamba jatan (upgradation) on turnkey basis under bn-9018002443

Read more
Construction of 220 kv gss lamba jatan (upgradation) (distt. nagaur) on turnkey basis under bn-9018002442

Construction of 220 kv gss lamba jatan (upgradation) (distt. nagaur) on turnkey basis under bn-9018002442

Read more
Click Here to Download Dockets
of your Industry type
Get customized tender Recommendations for your Enterprise