Tender Details
Beyond this tender, use our platform to source any product, service, or solution.
Get direct quotes or register as a qualified provider.
| Particulars | Details |
|---|---|
| Title |
Mtps I Mill Plant Unit Ii Dismantling And Assembling Of Coal Pipe Bends And Patch Welding The Eroded Portions Of Coal Bends Pipelines Between Mill Outlet Elbow And Fuel Inlet Elbow During Annual Overhaul 2025 26
|
| Description |
Mtps I Mill Plant Unit Ii Dismantling And Assembling Of Coal Pipe Bends And Patch Welding The Eroded Portions Of Coal Bends Pipelines Between Mill Outlet Elbow And Fuel Inlet Elbow During Annual Overhaul 2025 26
|
| Organisation | TNEB Limited | State Govt. and UT |
| Tender Id | 2025_EB_622791_1 |
|
Reference Number |
CE / MTPS-I / SE/ M-I /MP/ OT. 384 /2025-26 |
| Tender Fee | 0 |
| EMD | 7600 |
| Tender Value | - |
| Place | Mettur Thermal Power Station-I / Mettur Dam |
| Link |
View Original Tender Notice
https://tntenders.gov.in/nicgep/app?page=FrontEndTenderDetailsExternal&service=page&tnid=744726 |
| Start Date | November 12, 2025 23:00 |
| End Date |
Expired
26/11/2025
Expired 321 days ago |
Tender Support
Get help with filing, GeM registration, documents, or relevant tender alerts.
Mtps i mill plant unit ii dismantling and assembling of coal pipe bends and patch welding the eroded portions of coal bends pipelines between mill outlet elbow and fuel inlet elbow during annual overhaul 2026 27
Mtps i mill plant unit ii dismantling and assembling of coal pipe bends and patch welding the eroded portions of coal bends pipelines between mill outlet elbow and fuel inlet elbow during annual overhaul 2026 27
Read moreMtps i mill plant unit ii dismantling and assembling of coal pipes with bends and renewal of eroded pipes of length at about 15 mtr length along with bends between mill outlet elbow and fuel inlet elbow during aoh 2026 27
Mtps i mill plant unit ii dismantling and assembling of coal pipes with bends and renewal of eroded pipes of length at about 15 mtr length along with bends between mill outlet elbow and fuel inlet elbow during aoh 2026 27
Read moreMtps i mill plant unit ii dismantling and assembling of fuel inlet elbows and hard facing of fuel inlet elbows long and short during annual overhaul 2026 27
Mtps i mill plant unit ii dismantling and assembling of fuel inlet elbows and hard facing of fuel inlet elbows long and short during annual overhaul 2026 27
Read moreMtps i mill plant unit ii dismantling the eroded 90 degree ceralin coal bends from coal pipe lines and reconditioning the released one and assembling the reconditioned bends in an appropriate manner in the coal flow system during aoh 2026 27
Mtps i mill plant unit ii dismantling the eroded 90 degree ceralin coal bends from coal pipe lines and reconditioning the released one and assembling the reconditioned bends in an appropriate manner in the coal flow system during aoh 2026 27
Read moreMtps i mill plant unit ii removal of accumulated ash from the horizontal portions of the mill inlet pa hot air duct at 4 5 mtr 18 mtr level for mills 2a to 2f during annual overhaul 2026 27
Mtps i mill plant unit ii removal of accumulated ash from the horizontal portions of the mill inlet pa hot air duct at 4 5 mtr 18 mtr level for mills 2a to 2f during annual overhaul 2026 27
Read moreMtps i mill plant unit ii applying two layers ceramic wear coat eromat at mill outlet elbow released from unit ii during annual overhaul 2026 27
Mtps i mill plant unit ii applying two layers ceramic wear coat eromat at mill outlet elbow released from unit ii during annual overhaul 2026 27
Read moreMtps i mill plant unit ii patch welding of eroded portion of hot air ducts joints and coal mill 2a to 2f vertical inlet area above the horizontal area and below the expansion joint providing insulation for pa inlet duct in coal mills 2a to 2f during
Mtps i mill plant unit ii patch welding of eroded portion of hot air ducts joints and coal mill 2a to 2f vertical inlet area above the horizontal area and below the expansion joint providing insulation for pa inlet duct in coal mills 2a to 2f during
Read moreTtps operation circle mpm i unit iii replacement of eroded coal pipe lines, bends and fittings between mills d, e and f and boiler during the forthcoming overhaul
Ttps operation circle mpm i unit iii replacement of eroded coal pipe lines, bends and fittings between mills d, e and f and boiler during the forthcoming overhaul
Read moreTtps operation circle mpm i unit iii replacement of eroded coal pipe lines, bends and fittings between mills a, b and c and boiler during the forthcoming overhaul
Ttps operation circle mpm i unit iii replacement of eroded coal pipe lines, bends and fittings between mills a, b and c and boiler during the forthcoming overhaul
Read moreMtps i tm unit ii replacing the defective eroded drip line reducers expanders changing the defective eroded plug broken 1 and 2 drain line and vent line valves pipes bends by ibr and non ibr welding transporting the variable load hanger etc
Mtps i tm unit ii replacing the defective eroded drip line reducers expanders changing the defective eroded plug broken 1 and 2 drain line and vent line valves pipes bends by ibr and non ibr welding transporting the variable load hanger etc
Read moreof your Industry type