Tender Details

Particulars Details
Title
(A) Providing And Fixing Of L.T Control Panel 440 V, 800 A As Secondary Controlling Of 250 Kva, 3.3 Kv/440 V Transformer Installed At Main Sub Station At Gvp Phase Ii Ocp (B) Repairing And Re Winding Of 55 Kw, 440 V Make Wnp For Washing Station And Water S
Description
(A) Providing And Fixing Of L.T Control Panel 440 V, 800 A As Secondary Controlling Of 250 Kva, 3.3 Kv/440 V Transformer Installed At Main Sub Station At Gvp Phase Ii Ocp (B) Repairing And Re Winding Of 55 Kw, 440 V Make Wnp For Washing Station And Water S
Organisation Central Coalfields Limited | Public Sector Undertakings
Tender Id 2025_CCL_331464_1
Reference
Number
PE(E and M)/GVP Ph-II/E-Tender/2024-25/38 , Dt-06.03.2025
Tender Fee 0
EMD 3600
Tender Value -
Place Office of the Project Engineer (E and M), GVP Ph-I
Link
View Original Tender Notice

https://coalindiatenders.nic.in/nicgep/app?page=FrontEndTenderDetailsExternal&service=page&tnid=343590

Start Date March 07, 2025 19:30
End Date
Expired 19/03/2025

Expired 575 days ago

Search Similar tenders?

Tender Support

Get help with filing, GeM registration, documents, or relevant tender alerts.

Similar Tenders
Repairing and rewinding of 02 nos. of distribution transformers, 250kva, 11kv/440v and 250kva, 3.3kv/440v installed at cisf colony and gurudwara chowk under gm unit nk area.

Repairing and rewinding of 02 nos. of distribution transformers, 250kva, 11kv/440v and 250kva, 3.3kv/440v installed at cisf colony and gurudwara chowk under gm unit nk area.

Read more
Complete rewinding/ repairing of 250kva, 3.3kv/440v transformer at peocp under hazaribag area.

Complete rewinding/ repairing of 250kva, 3.3kv/440v transformer at peocp under hazaribag area.

Read more
Repairing/rewinding of 250kva, 11kv/440v transformer and 100kva,3.3kv/440v transformer at topa project under kuju area.

Repairing/rewinding of 250kva, 11kv/440v transformer and 100kva,3.3kv/440v transformer at topa project under kuju area.

Read more
Repairing of l.t control panel for controlling of power supply for colonies, 415v, 800a sl. no. 2516 make-l and t, installed at old mines sawang - gvp ph-ii ocp.

Repairing of l.t control panel for controlling of power supply for colonies, 415v, 800a sl. no. 2516 make-l and t, installed at old mines sawang - gvp ph-ii ocp.

Read more
Dehydration, filtration corksheet change and required studs of 300kva 3.3kv 440v (2nos), 250kva 3.3kv 440v at 4 no colony and 250kva 11kv 440v at main substation lightening transformer in of bankola colliery under bankola area (at site)

Dehydration, filtration corksheet change and required studs of 300kva 3.3kv 440v (2nos), 250kva 3.3kv 440v at 4 no colony and 250kva 11kv 440v at main substation lightening transformer in of bankola colliery under bankola area (at site)

Read more
(a)complete repairing and rewinding of 01 no. 315kva, 11kv/440v, si.no. wnp distribution transformer used for power distribution to rawani-tola under kathara colliery, kathara area. (b) complete repairing /rewinding of 01 no. 250kva, 3.3kv/440v trans

(a)complete repairing and rewinding of 01 no. 315kva, 11kv/440v, si.no. wnp distribution transformer used for power distribution to rawani tola under kathara colliery, kathara area. (b) complete repairing /rewinding of 01 no. 250kva, 3.3kv/440v trans

Read more
Repairing and rewinding of 03 nos. transformer of rating 250kva, 3.3kv/440v and 02 nos. 25kva. 3.3kv/440v transformer installed at different locations of topa project under kuju area.

Repairing and rewinding of 03 nos. transformer of rating 250kva, 3.3kv/440v and 02 nos. 25kva. 3.3kv/440v transformer installed at different locations of topa project under kuju area.

Read more
Complete repairing / rewinding 01 no. 315 kva. 3.3kv/440v transformer with si.no wnp installed at jhirkey basti under kathara colliery.

Complete repairing / rewinding 01 no. 315 kva. 3.3kv/440v transformer with si.no wnp installed at jhirkey basti under kathara colliery.

Read more
Repairing and re-winding of 325kw, 3.3kv, make-marathan, h.t motor, sl.no.-3f330720/2 of gvp ph-ii ocp

Repairing and re-winding of 325kw, 3.3kv, make-marathan, h.t motor, sl.no.-3f330720/2 of gvp ph-ii ocp

Read more
Complete repairing of 800a, 440v, gec make ocb switch s.n.- 40/0520 controlling of mathadih colony lighting line under abc colliery.

Complete repairing of 800a, 440v, gec make ocb switch s.n.- 40/0520 controlling of mathadih colony lighting line under abc colliery.

Read more
Click Here to Download Dockets
of your Industry type
Get customized tender Recommendations for your Enterprise