Tender Details
Particulars | Details |
---|---|
Title |
Balance Work Of Jjm Piped Water Supply Scheme Under Jal Jeevan Mission At Village Umrikala Block Pichhore Distt
|
Description |
Balance Work Of Jjm Piped Water Supply Scheme Under Jal Jeevan Mission At Village Umrikala Block Pichhore Distt
|
Organisation | Public Health Engineering- O/o Engineer In Chief | State Govt. and UT |
Tender Id |
AAAAAAAAAA Login to view |
Reference Number |
AAAAAAAAAA Login to view |
Tender Fee | 11047 |
EMD | 89000 |
Tender Value | |
Place | Block Pichhore |
Link |
AAAAAAAAAA Login to view |
Start Date | May 20, 2025 16:00 |
End Date |
03/06/2025 ( 15 days left ) Search Similar tenders? |
Join for More Relevant Opportunities |
Supply, installation and commissioning of water spray system at conveyor belt 1a, 1b, 1c, 1d, 2a1, 2b1, 2a, 2b, 2c, 2d, 3a, 3b, 3c and 3d at ktps under capex 24-25
Supply, installation and commissioning of water spray system at conveyor belt 1a, 1b, 1c, 1d, 2a1, 2b1, 2a, 2b, 2c, 2d, 3a, 3b, 3c and 3d at ktps under capex 24-25
Read moreTender for annual maintenance of water supply pipe and other allied work at zone 22 of indore municipal corporation.
Tender for annual maintenance of water supply pipe and other allied work at zone 22 of indore municipal corporation.
Read moreQuality improvement of drinking water supply by way of construction of 8 nos. 5000 gph capacity package type iron removal plant (irp) and 03 nos. pump house at different places under the jurisdiction of dws sub-division, salema.
Quality improvement of drinking water supply by way of construction of 8 nos. 5000 gph capacity package type iron removal plant (irp) and 03 nos. pump house at different places under the jurisdiction of dws sub-division, salema.
Read moreSupply, installation, testing and commissioning of table-top afm/stm system for ambient operation with vibration isolation stage and advanced imaging options
Supply,&#x0d installation, testing and commissioning of table-top afm/stm system for ambient operation with&#x0d vibration isolation stage and advanced imaging options at the department of physics, kannur university (under pm usha scheme)
Read moreLining of w/c at outlet rd ...
Estimate for construction of w/c at outlet rd 2900/l direct barsola feeder in the land of dhan raj s/o gopala field to sadhu s/o ramchander field (14 acre) village baroda (under mplad scheme)
Read moreAutomation and upgradation of existing water supply system including outsourcing for monitoring, management and operation of the same at binnaguri mil station under ge (s) binnaguri
Automation and upgradation of existing water supply system including outsourcing for monitoring, management and operation of the same at binnaguri mil station under ge (s) binnaguri
Read moreEmpanelment of agencies for supply of different glasswares and miscellaneous items for various water testing laboratories under jjm, assam
Empanelment of agencies for supply of different glasswares and miscellaneous items for various water testing laboratories under jal jeevan mission, assam
Read moreMtc of type ii iii and iv qtr total 24 nos under kumarghat sub divisional hospital during the year 2024 25 sh r c c work finishing work water supply and sanitary line etc
Mtc of type ii iii and iv qtr total 24 nos under kumarghat sub divisional hospital during the year 2024 25 sh r c c work finishing work water supply and sanitary line etc
Read moreBalance work for construction of security barrack at 400 kv gis substation chandwa under jipp a1 project
Balance work for construction of security barrack at 400 kv gis substation chandwa under jipp a1 project
Read moreChambal alwar bharatpur water supply project package 2 based on hybrid annuity model ace(p) bharatpur nit no. 05 / 2024-25
Work of construction of intermediate cwph at kotra baseri laying of clear water transmission main from kotra to naroli nadbai via junction 2 at naroli ips nadbai nagar ramgarh kishangarhbas tijara jairoli and bhiwadi based on ham model under jjm