| Particulars | Details |
|---|---|
| Title |
Estimate For Add. 3.15 Mva Ptr In Junapani S/S Under Boliya Dc, Garoth Division. Administrative Approval Md/Wz/08 03/3998 Indore Date 17 03 2025
|
| Description |
Estimate For Add. 3.15 Mva Ptr In Junapani S/S Under Boliya Dc, Garoth Division. Administrative Approval Md/Wz/08 03/3998 Indore Date 17 03 2025
|
| Organisation | Madhya Pradesh Paschim Kshetra Vidyut Vitran Company Ltd | State Govt. and UT |
| Tender Id | 2025_MPPKV_428991_1 |
|
Reference Number |
EE/STC/MDS/124/785/04-06-2025 |
| Tender Fee | 1295 |
| EMD | 5000 |
| Tender Value | - |
| Place | EE STC MANDSAUR |
| Link |
View Original Tender Notice
https://mptenders.gov.in/nicgep/app?page=FrontEndTenderDetailsExternal&service=page&tnid=505698 |
| Start Date | June 06, 2025 20:30 |
| End Date |
Expired
13/06/2025
Expired 489 days ago |
Tender Support
Get help with filing, GeM registration, documents, or relevant tender alerts.
Administrative approval letter no md/wz/08-03/6738 inodre dt. 08.04.2026 for new 33 kv line from 132 ehv karwakhedi to khelukheda ss to bifurcate overloaded 33 kv feeder asavata of tal r d/c under sstd scheme 2026-27
Administrative approval letter no md/wz/08-03/6738 inodre dt. 08.04.2026 for new 33 kv line from 132 ehv karwakhedi to khelukheda ss to bifurcate overloaded 33 kv feeder asavata of tal r d/c under sstd scheme 2026-27
Read moreAn estimate framed for the arrangement of double supply to increase reliability of 33 kv bus stand feeder from 220/33kv gwaltoli substation under sstd scheme via administrative approval letter no md/wz/08-03/6738 dated 09.04.2026 neemuch division
An estimate framed for the arrangement of double supply to increase reliability of 33 kv bus stand feeder from 220/33kv gwaltoli substation under sstd scheme via administrative approval letter no md/wz/08-03/6738 dated 09.04.2026 neemuch division
Read moreAn estimate framed for the additional 33kv line for alternative supply of 33/11kv industrial area s/s from 132/33kv gwaltoli substation neemuch via administrative approval of md/wz/08-03/6738 dated 09.04.2026 neemuch town under neemuch division
An estimate framed for the additional 33kv line for alternative supply of 33/11kv industrial area s/s from 132/33kv gwaltoli substation neemuch via administrative approval of md/wz/08-03/6738 dated 09.04.2026 neemuch town under neemuch division
Read moreAn estimate framed for interconnection of 33 kv line from 33/11kv crpf substation to 33/11kv kileshwar substation to provide additional supply for reliability under sstd scheme via administrative approval letter no md/wz/08-03/6738 dated 09/04/2026
An estimate framed for interconnection of 33 kv line from 33/11kv crpf substation to 33/11kv kileshwar substation to provide additional supply for reliability under sstd scheme via administrative approval letter no md/wz/08-03/6738 dated 09/04/2026
Read moreEstimate for as per the sanction estimate under sstd scheme of khetakheda substation capacity 3.15 mva ptr the estimate has been framed accordingly. reff. latter no. md/wz/08/03-3998 dt. 17-03-2025 and md/wz/08/03-16788 dt. 20-11-2025. under harkiyak
Estimate for as per the sanction estimate under sstd scheme of khetakheda substation capacity 3.15 mva ptr the estimate has been framed accordingly. reff. latter no. md/wz/08/03-3998 dt. 17-03-2025 and md/wz/08/03-16788 dt. 20-11-2025. under harkiyak
Read moreEstimate for additional of power transformer from 3.15 mva at 33/11 kv s/s darukheda under r-2 dc estimate is framed as per administrative approval no.md/wz/08-03/3998 indore date 17-03-25. under neemuch division
Estimate for additional of power transformer from 3.15 mva at 33/11 kv s/s darukheda under r-2 dc estimate is framed as per administrative approval no.md/wz/08-03/3998 indore date 17-03-25. under neemuch division
Read moreEstimate for augmentation of ptr-i at 33/11 kv substation shamgarh with administrative approval for augmentation of power transformer under sstd scheme 2024-25 from gomp fund via section number md/wz/08-03/3998 indore dated 17.03.2025
Estimate for augmentation of ptr-i at 33/11 kv substation shamgarh with administrative approval for augmentation of power transformer under sstd scheme 2024-25 from gomp fund via section number md/wz/08-03/3998 indore dated 17.03.2025
Read moreEstimate for installation of add 3.15 mva for ovecoming loading on power transformer at akyadeh s/s under sstd (2023-24) administrative approval md/wz/08-03/4761 date 31-03-2023on semi turn key mode
Estimate for installation of add 3.15 mva for ovecoming loading on power transformer at akyadeh s/s under sstd (2023-24) administrative approval md/wz/08-03/4761 date 31-03-2023on semi turn key mode
Read moreEstimate for installation of add 3.15 mva for ovecoming loading on power transformer at akyadeh s/s under sstd (2023-24) administrative approval md/wz/08- 03/4761 date 31-03- 2023on semi turn key mode
Estimate for installation &#x0d of add 3.15 mva for &#x0d ovecoming loading on &#x0d power transformer at &#x0d akyadeh s/s under sstd &#x0d (2023-24) administrative &#x0d approval md/wz/08-&#x0d 03/4761 date 31-03-&#x0d 2023on semi turn key mode
Read moreEstimate for as per administrative approval no.md wz 08-03 9527 date 23.06.2025 estimate prepared for new 3.15 mva ptr 33 11kv substation kelukheda under sstd scheme in tal rural dc onm division alote
Estimate for as per administrative approval no.mdwz08-039527 date-23.06.2025 estimate prepared for new 3.15 mva ptr 3311kv substation kelukheda under sstd scheme in tal rural dc onm division alote
Read moreof your Industry type