🏭 Procurement Opportunity: Regrouping Of Tf And Capacity Enhancement Under Edd Iii Jnp 🔧💼 Purvanchal Vidyut Vitran Nigam Limited (Pvvnl), Varanasi, A State Government Undertaking, Invites Bids For The Work Of Regrouping Of Transformer Farms (Tf) And Capacity Enhancement Under The Electric Mobility And Smart Grid Programme (Edd Iii Jnp). 📅 Bid Submission Deadline: April 05, 2024, 4:00 Pm Tender Fee: Inr 3540 Emd: Inr 28000 Interested Bidders Must Possess The Requisite Expertise And Experience In Executing Similar Projects. Proposals Should Encompass Detailed Project Plans, Technical Specifications, Cost Estimates, And Timelines For Project Completion. Keywords: Regrouping Of Tf, Capacity Enhancement, Edd Iii Jnp, Purvanchal Vidyut Vitran Nigam Limited, Electric Mobility And Smart Grid Programme, Government Tender, Bid Submission, Tender Fee, Earnest Money Deposit (Emd)| Particulars | Details |
|---|---|
| Title |
Work For Regrouping Of Tf And Capacity Enhancement Under Edd Iii Jnp
|
| Description |
Work For Regrouping Of Tf And Capacity Enhancement Under Edd Iii Jnp
|
| Organisation | Purvanchal Vidyut Vitran Nigam Limited Varanasi | State Govt. and UT |
| Tender Id | 2024_PVVNV_919143_1 |
|
Reference Number |
108/EDC-I(Jnp)/2023-24 |
| Tender Fee | 3540 |
| EMD | 28000 |
| Tender Value | - |
| Place | work |
| Link |
View Original Tender Notice
https://etender.up.nic.in/nicgep/app?page=FrontEndTenderDetailsExternal&service=page&tnid=1588271 |
| Start Date | March 18, 2024 22:30 |
| End Date |
Expired
05/04/2024
Expired 922 days ago |
Tender Support
Get help with filing, GeM registration, documents, or relevant tender alerts.
Capacity enhancement of 12.5mva transformer no1 to 20mva transformer
Capacity enhancement of existing 1x12.5mva, 110/11kv transformer no.1 with 1x20mva, 110/11kv transformer under 110kv substation, punalur - erection and commissioning of 20mva transformer no.1
Read moreCapacity enhancement of 110 kv palakkadvennakkara 110kv dc line
Capacity enhancement of 110 kv palakkadvennakkara 110kv dc line from 220 kv substation palakkad to 110 kv substation vennakkara by reconductoring of acsr wolf to al59,195 sqmm including supply, installation testing and commissioning
Read moreProvision of 82.5kva and 180kva dg sets backup for transit facilities at tf-i tf-iii, major quarter (mq) and tf-v at cv raman nagar, bangalore
Provision of 82.5kva and 180kva dg sets backup for transit facilities at tf-i tf-iii, major quarter (mq) and tf-v at cv raman nagar, bangalore
Read moreRfp for enhancement of storage capacity of cctvs surveillance system at cfs, navi mumbai
Rfp for enhancement of storage capacity of cctvs surveillance system at cfs, navi mumbai
Read moreCarriage of distribution transformer of different capacity under edd- lalgang azamarh.
Carriage of distribution transformer of different capacity under edd- lalgang azamarh.
Read moreCivil work enhancement of existing 110 22 kv power transformer capacity at cumbum 110 22 kv ss
Civil work enhancement of existing 110 22 kv power transformer capacity at cumbum 110 22 kv ss
Read moreCivil work for enhancement of existing 110/22 power transformer capacity at periyakulam 110/22 kv ss
Civil work for enhancement of existing 110/22 power transformer capacity at periyakulam 110/22 kv ss
Read moreWork of separate earthing for 36 no. lightning arresters installed of 36 no. power tf across 19 no. s/s under the edd- mirzapur to ensure equipment safety as part of the b.p. 2026-27.
Work of separate earthing for 36 no. lightning arresters installed of 36 no. power tf across 19 no. s/s under the edd- mirzapur to ensure equipment safety as part of the b.p. 2026-27.
Read moreWork of separate earthing for 29 no. lightning arresters installed of 29 no. power tf across 16 no. s/s under the edd-chunar mirzapur to ensure equipment safety as part of the b.p. 2026-27.
Work of separate earthing for 29 no. lightning arresters installed of 29 no. power tf across 16 no. s/s under the edd-chunar mirzapur to ensure equipment safety as part of the b.p. 2026-27.
Read moreWork of separate earthing for 36 no. lightning arresters installed of 36 no. power tf across 19 no. s/s under the edd-kachhwa mirzapur to ensure equipment safety as part of the b.p. 2026-27.
Work of separate earthing for 36 no. lightning arresters installed of 36 no. power tf across 19 no. s/s under the edd-kachhwa mirzapur to ensure equipment safety as part of the b.p. 2026-27.
Read moreof your Industry type