Tender Details
Check your funding eligibility in 2 minutes.
Answer a few questions and our team will contact you with your best options.
Particulars | Details |
---|---|
Title |
Installation, Alignment And Commissioning Of Pumps With Sel Engine And Electric Motor, Laying Of Ms Pipeline With Flange Welding, Fabrication Of Tee And Bends, Collection Of Pipes, Dismantling Of Ms Pipes And Other Miscellaneous Work In Kaniha Ocp
|
Description |
Installation, Alignment And Commissioning Of Pumps With Sel Engine And Electric Motor, Laying Of Ms Pipeline
With Flange Welding, Fabrication Of Tee Andends, Collection Of Pipes, Dismantling Of Ms Pipes And Other Miscellaneous Work In Kaniha Ocp
|
Organisation | Mahanadi Coalfields Limited | Public Sector Undertakings |
Tender Id | 2025_MCL_333302_1 |
Reference Number |
MCL/KA/EnM/e-tender/ 2024-25/332 Dt. 26.03.2025 |
Tender Fee | 0 |
EMD | 98100 |
Tender Value | |
Place | Kaniha OCP |
Link | https://coalindiatenders.nic.in/nicgep/app?page=FrontEndTenderDetailsExternal&service=page&tnid=345507 |
Start Date | March 27, 2025 15:30 |
End Date |
15/04/2025 ( Expired 69 days ago ) Search Similar tenders? |
Join for More Relevant Opportunities |
Supply, installation, configuration, testing and commissioning of network infrastructure deployment across various substations and the rhq under powergrid eastern region-ii along with all the accessories, laying of cables and pvc pipes
Supply, installation, configuration, testing and commissioning of network infrastructure deployment across various substations and the rhq under powergrid eastern region-ii along with all the accessories, laying of cables and pvc pipes
Read moreProviding sewage water pumping system with construction of collection sump, erection of motor, laying of hdpe pipes and accessories to the ponram apartment at kurinchi nagar in division no 2 of suramangalam ward office.
Providing sewage water pumping system with construction of collection sump, erection of motor, laying of hdpe pipes and accessories to the ponram apartment at kurinchi nagar in division no 2 of suramangalam ward office.
Read moreFabrication of connecting flange of suction and delivery side of 2nos horizontal flow more pumps with making of both side flanges of nrv and sv of hingula ocp.
Fabrication of connecting flange of suction and delivery side of 2nos horizontal flow more pumps with making of both side flanges of nrv and sv of hingula ocp.
Read moreDi of pipeline 300 mtrs length, dia 6 inch (dismantling, transporting ,laying, jointing)at nichitpur ocp(ii) and installation of ms pipe 100mm 4 inch digging laying, jointing, refilling, welding etc
Di of pipeline 300 mtrs length, dia 6 inch (dismantling, transporting ,laying, jointing)at nichitpur ocp(ii) and installation of ms pipe 100mm 4 inch digging laying, jointing, refilling, welding etc
Read moreLaying, erection of 8 inch pipe range 450mtrs with pump-motor, base plate installation, tanker filling point fabrication and switch-er laying at block-iv ocp departmental patch under govindpur area
Laying, erection of 8 inch pipe range 450mtrs with pump-motor, base plate installation, tanker filling point fabrication and switch-er laying at block-iv ocp departmental patch under govindpur area
Read more(1) cutting dismantling fabrication of weigh bridge of re-installation commissioning welding with cleaning of weigh bridge sijua siding weigh bridge,under katras area
(1) 
 cutting dismantling 
 fabrication of weigh 
 bridge of re-installation 
 commissioning 
 welding 
 with cleaning of weigh 
 bridge sijua siding weigh 
 bridge,under katras area
Read moreMtps i mill plant unit i fabrication of various length of dia 40 nb cooling water pipe line with flanges and assembling in the cooler cover of mill 1a to 1f and dismantling of seal air fan motor and overhauling reassembling setting the alignment
Mtps i mill plant unit i fabrication of various length of dia 40 nb cooling water pipe line with flanges and assembling in the cooler cover of mill 1a to 1f and dismantling of seal air fan motor and overhauling reassembling setting the alignment
Read moreComplete overhauling and repairing of 01 no. 2000 gpm pump, name plate missing, 3chr, make mnp and onsite commissioning of the pump on the base plate and alignment with the three phase induction motor in mine w.r.t. karo ocp, bnk area
Complete overhauling and repairing of 01 no. 2000 gpm pump, name plate missing, 3chr, make mnp and onsite commissioning of the pump on the base plate and alignment with the three phase induction motor in mine w.r.t. karo ocp, bnk area
Read moreDismantling and laying of 8 inch dia m.s. pipeline required for extension of delivery pipeline of the 2000 g.p.m. pump motor set installed at the a patch in mine, involved in dewatering of the a patch, w.r.t. karo ocp, under bnk area
Dismantling and laying of 8 inch dia m.s. pipeline required for extension of delivery pipeline of the 2000 g.p.m. pump motor set installed at the a patch in mine, involved in dewatering of the a patch, w.r.t. karo ocp, under bnk area
Read moreInstallation of 01 no. pump-motor sets at kcc coal patch along with laying and jointing of pipeline at dipka expansion project.
Installation of 01 no. pump-motor sets at kcc coal patch along with laying and jointing of pipeline at dipka expansion project.
Read moreof your Industry type