🔧 Custom Bid Invitation: Annual Overhauling Of Lp Turbine Generator 🔧 The Ministry Of Power, Through Its Contracts And Materials Division, Is Seeking Proposals For The Annual Overhauling Of A Low Pressure (Lp) Turbine Generator, Including The Inspection Of Turbines. 🏭 🗓️ Deadline: April 24, 2024, 7:00 Pm Service Providers With Expertise In Overhauling And Inspecting Lp Turbine Generators Are Invited To Submit Detailed Proposals, Outlining Their Methodology, Experience, And Pricing. Keywords: Ministry Of Power, Lp Turbine Generator, Overhauling, Inspection, Custom Bid, Government Contract| Particulars | Details |
|---|---|
| Title |
Custom Bid For Services Annual Overhauling Of Lp Turbine Generator Along With Inspection Of Turb
|
| Description |
|
| Organisation | Contracts and Materials | Ministry of Power |
| Tender Id | GEM/2024/B/4850353 |
|
Reference Number |
- |
| Tender Fee | - |
| EMD | - |
| Tender Value | 2 Crore |
| Place | |
| Link |
View Original Tender Notice
https://bidplus.gem.gov.in/all-bids |
| Start Date | April 10, 2024 22:56 |
| End Date |
Expired
24/04/2024
Expired 904 days ago |
Tender Support
Get help with filing, GeM registration, documents, or relevant tender alerts.
Award of Contract & Bid Results
BHARAT HEAVY ELECTRICALS LIMITED
68242940
Technical Evaluation Results
| S.No. | Seller Name | Participated On | MSE/MII Status | Status |
|---|---|---|---|---|
| 1 | BHARAT HEAVY ELECTRICALS LIMITED | 20-07-2024 17:05:16 | N/A | Qualified |
| 2 | Laxmi Enterprises | 21-07-2024 22:44:06 | N/A | Disqualified |
Financial Evaluation Results
| S.No. | Seller Name | Offered Item | Total Price | Rank |
|---|---|---|---|---|
| 1 | BHARAT HEAVY ELECTRICALS LIMITED | Item Categories : Custom Bid for Services - Annual Overhauling of LP Turbine Generator along with inspection of Turb | 69033540.00 | L1 |
Ordered Items & Contract Pricing
| Service | Category Name | Ordered Quantity | Price |
|---|---|---|---|
| Custom Bid for Services - Annual Overhauling of LP Turbine Generator along with inspection of Turbine Bearing Valves and other associated works of Unit No 8 250 MW of CTPS DVC | Custom Bid for Services | 1 | ₹ 68242940.000 |
Ttps mech ii tm i unit iii inspection overhauling rectification of condenser steam side longitudinal bellows hp lp bypass valves and oil system steam and condensate valves for main turbine system during the forthcoming annual overhaul
Ttps mech ii tm i unit iii inspection overhauling rectification of condenser steam side longitudinal bellows hp lp bypass valves and oil system steam and condensate valves for main turbine system during the forthcoming annual overhaul
Read moreTtps mechii tm ii unitiv kwu turbine inspection overhauling and commissioning of actuators of steam line valves during annual overhaul 2026 27
Ttps mechii tm ii unitiv kwu turbine inspection overhauling and commissioning of actuators of steam line valves during annual overhaul 2026 27
Read moreTtps mechii tm ii unitv kwu turbine inspection overhauling and commissioning of actuators of steam line valves during annual overhaul 2026 27
Ttps mechii tm ii unitv kwu turbine inspection overhauling and commissioning of actuators of steam line valves during annual overhaul 2026 27
Read moreTtps mechii tm i unitiii inspection overhauling of hpt ipt control valves cam shaft assemblies and turbine bearings during the forthcoming annual overhaul
Ttps mechii tm i unitiii inspection overhauling of hpt ipt control valves cam shaft assemblies and turbine bearings during the forthcoming annual overhaul
Read moreSupply of lp turbine lead diaphragms for unit-3,4 of tm division/stage-ii/btps
Supply of lp turbine lead diaphragms for unit-3,4 of tm division/stage-ii/btps
Read moreMa17st00t343109200-turbine rotor centring tool along with hex head stud
Ma17st00t343109200-turbine rotor centring tool along with hex head stud
Read moreDesign and development of technology demonstrator of 25kw part electric gas turbine generator
Design and development of technology demonstrator of 25kw part electric gas turbine generator
Read moreCapital overhauling service contract for kudgi unit 3 generator and tg steam valves overhauling works
Capital overhauling service contract for kudgi unit 3 generator and tg steam valves overhauling works