Particulars | Details |
---|---|
Title |
Complete Erection Work Of 01 No. 132 Kv Bus Coupler Bay At 132 Kv Sub Station Sironj Under Ee Testing Dn. Mpptcl Vidisha, Against Nit Tender Specification No. 3373000/2024 25/Ts 03.
|
Description |
Complete Erection Work Of 01 No. 132 Kv Bus Coupler Bay At 132 Kv Sub Station Sironj Under Ee Testing Dn. Mpptcl Vidisha, Against Nit Tender Specification No. 3373000/2024 25/Ts 03.
|
Organisation | MP Power Transmission Co. Ltd. | State Govt. and UT |
Tender Id | 2024_MPPTC_358444_1 |
Reference Number |
3373000/2024-25/TS-03. |
Tender Fee | 885 |
EMD | 5000 |
Tender Value | |
Place | Sironj 132KV Substation |
Link | https://mptenders.gov.in/nicgep/app?page=FrontEndTenderDetailsExternal&service=page&tnid=421436 |
Start Date | July 20, 2024 00:00 |
End Date |
07/08/2024 ( Expired 315 days ago ) Search Similar tenders? |
Join for More Relevant Opportunities |
Construction of 2x500 mva, 400/220 kv sub-station at amber (jaipur-north) (distt.jaipur) including supply of all equipments/materials, erection (including civil works), testing and commissioning (on turnkey basis) against specification no. rvpn/ehv/b
Construction of 2x500 mva, 400/220 kv sub-station at amber (jaipur-north) (distt.jaipur) including supply of all equipments/materials, erection (including civil works), testing and commissioning (on turnkey basis) against specification no. rvpn/ehv/b
Read moreFor supply and work for construction of new 01 nos 33 kv supreme bay against deposit work at 132 kv sub station pukhrayan kanpur dehat under etd-i kanpur
For supply and work for construction of new 01 nos 33 kv supreme bay against deposit work at 132 kv sub station pukhrayan kanpur dehat under etd-i kanpur
Read moreConstruction of 01 no. 33 kv radha gulmohar bay at 132 kv sub-station mathura-ii, mathura.
Construction of 01 no. 33 kv radha gulmohar bay at 132 kv sub-station mathura-ii, mathura.
Read moreFor the work of carriage/erection of 132 kv bus pt with structures at 132 kv sub station mehnagr and koilsa under etd azamgarh
For the work of carriage/erection of 132 kv bus pt with structures at 132 kv sub station mehnagr and koilsa under etd azamgarh
Read moreConstruction work of 2 nos -132kv feeder bay work at 400 kv s/s chhegaon (torni) substation for pump house - 01 and 02 and 1 no 33kv bay at 132kv chhegaon substation for pump house 03 and 1 nos 33kv bay at 132kv zhirniya substation for pump house - 4
Construction work of 2 nos -132kv feeder bay work at 400 kv s/s chhegaon (torni) substation for pump house - 01 and 02 and 1 no 33kv bay at 132kv chhegaon substation for pump house 03 and 1 nos 33kv bay at 132kv zhirniya substation for pump house - 4
Read moreWbpwd/rds/nit-03 (sl. no.01)/25-26/ee/mhd
Road marking and road furniture work for godapiasal - anandapur - keshpur road from 0.00 kmp to 15.350 kmp under midnapore highway division in the district of paschim medinipur.
Read moreBarwani 132 kv bus coupler erecion work
Erection work of construction of 1 no. 132 kv bus coupler bay at barwani 132 kv sub-station.
Read moreAnnual housekeeping work of 220 132 33 kv grid sub station lalmatia for the period from 01 07 2025 to 31 03 2026 i e 9 months for f y 2025 26
Annual housekeeping work of 220 132 33 kv grid sub station lalmatia for the period from 01 07 2025 to 31 03 2026 i e 9 months for f y 2025 26
Read moreAnnual housekeeping work of 220 132 33 kv grid sub station godda for the period from 01 07 2025 to 31 03 2026 i e 9 months for f y 2025 26
Annual housekeeping work of 220 132 33 kv grid sub station godda for the period from 01 07 2025 to 31 03 2026 i e 9 months for f y 2025 26
Read moreAnnual housekeeping work of 132 33 kv grid sub station sahibganj for the period from 01 07 2025 to 31 03 2026 i e 9months for f y 2025 26
Annual housekeeping work of 132 33 kv grid sub station sahibganj for the period from 01 07 2025 to 31 03 2026 i e 9months for f y 2025 26
Read moreof your Industry type